General Manager Update

MAY UPDATE 2026

Dear Members,
 
We are set to begin a significant and much-needed driveway project on Monday, May 11th. During this time, the usual flow of traffic at the club will be impacted. Staff will be onsite daily to assist with parking and shuttle services.
 
The project will be completed in three phases:
 

– Phase 1: Work begins on the steep hill from the clubhouse to the valet lot. This 70′ x 22′ area will be replaced with 6″ of wire-mesh reinforced concrete, which will better withstand heavy traffic and braking.

– Phase 2: The valet lot will be milled and completely repaved.

– Phase 3: The main driveway will be milled and repaved. We will work on one half of the driveway at a time to maintain traffic flow.
 
We anticipate the entire project will take approximately one week to complete. We will send daily updates regarding parking and shuttle services to keep you informed of each day’s progress.
 
Thank you for your patience as we complete these necessary upgrades to our facility.

Irrigation Update

As previously discussed, Fred Ode approved the installation of a much-needed new irrigation system for the golf course. We have entered into a contract with Commercial Irrigation, who will oversee the construction and installation of the new system.

This project is scheduled to begin in the fall and, weather permitting, will be completed before winter arrives in Ohio. The installation process is expected to have minimal impact on daily play. All new irrigation lines will be bored underground, and the construction crew will work on one hole at a time to limit disruptions.

After extensive planning and coordination, we are pleased to share that a working model of the new system has been finalized. The most noticeable improvement for players will be more consistent course conditions. This does not mean increased water usage—on the contrary, the new system will operate more efficiently, using less water while providing better overall coverage. Additionally, our team will gain the ability to target specific dry areas, a capability we currently lack.

This significant investment will greatly enhance the overall maintenance of the property and elevate the playing experience at Columbia Hills. We will provide additional updates as construction schedules are finalized.

Mike Jaeger

General Manager